Question1: What does a project jump-start include for a new implementation of SAP S/4HANA on-premise edition?
Please choose the correct answer.
Response:

Question2: In which phase do you create an ordered list of everything that is known to be needed in the product"?
Please choose the correct answer.
Response:

Question3: What does SAP Activate recommend to keep team members informed and aligned?
Please choose the correct answer.
Response:

Question4: In which SAP Activate methodology phase does the team identify and design functional quick wins in scope of the conversion project?
Please choose the correct answer.
Response:

Question5: How many deliverables are a part of the Key Deliverable 'Project Initiation'?
Please choose the correct answer.
Response:

Question6: Via which media does SAP provide Ready-to-run systems for SAP S/4HANA deployments?
There are 2 correct answers to this question.
Response:

Question7: What is the most granular level of the methodology you can view in the SAP Roadmap Viewer?
Please choose the correct answer.
Response:

Question8: What do you do during Sprint Execution?
Please choose the correct answer.
Response:

Question9: What accelerator can help you document the Configuration Definition in the Explore phase?
Please choose the correct answer.
Response:

Question10: What are key characteristics of the implementation approach in SAP Activate Methodology?
There are 3 correct answers to this question.
Response:

Question11: Which statements are part of the 5 Golden Rules for SAP S/4HANA Cloud, Single Tenant Edition?
There are 2 correct answers to this question.
Response:

Question12: What must you do when you implement SAP Business Suite On-Premise with SAP Best Practices?
Please choose the correct answer.
Response:

Question13: What is the objective of a sprint retrospective meeting?
Please choose the correct answer.
Response:

Question14: Which artifacts in the Testing work stream are created within the Realize phase for the New Implementation of SAP S/4HANA Cloud" transition path?
There are 2 correct answers to this question.
Response:

Question15: What are deliverables of the Application: Integration work stream in the prepare phase?
There are 3 correct answers to this question.
Response:

Question16: Which of the following are part of the 10 SAP Quality Principles?
There are 2 correct answers to this question.
Response:

Question17: Which of the following content best outlines the sequence of testing within the Application Design and Configuration work stream in the Realize phase?
Please choose the correct answer.
Response:

Question18: What is a Strategy Level 0 (LO) artifact?
Please choose the correct answer.
Response:

Question19: What Sprint types are part of the SAP Activate Methodology?
There are 3 correct answers to this question.
Response:

Question20: Which collaboration features can SAP Activate Jam users access?
There are 2 correct answers to this question.
Response:

Question21: In which phase do you verify that the SAP Best Practices content meets the customer's business needs, and then capture gaps?
Please choose the correct answer.
Response:

Question22: In which SAP Activate methodology phase does the team complete the Integration Validation?
Please choose the correct answer.
Response:

Question23: Which estimation technique can be used in Agile project delivery to size the user stories during sprint planning?
Please choose the correct answer.
Response:

Question24: Your project is preparing for the Fit/Gap analysis workshops. If you use the Agile approach, what sequence of activities do you perform in the Explore Phase?
Please choose the correct answer.
Response:

Question25: Which of the following is a Key Deliverable of the Prepare phase?
Please choose the correct answer.
Response:

Question26: How does the provisioning of SAP S/4HANA Cloud differ from the setup of SAP S/4HANA?
There are 2 correct answers to this question.
Response:

Question27: Where can you find Project Library Accelerators?
Please choose the correct answer.
Response:

Question28: What tool provides guidance on replacing custom code developed for SAP ERP with SAP S/4HANA functionality for the "System Conversion" transition path?
Please choose the correct answer.
Response:

Question29: Where can you find Data Migration templates?
Please choose the correct answer.
Response:

Question30: How are the build and test tasks planned and executed in the Realize phase?
Please choose the correct answer.
Response:

Question31: What tool is used to synchronize changes between SAP ERP and SAP S/4HANA maintenance tracks?
Please choose the correct answer.
Response:

Question32: What are two important approaches, based on the Control Center concept that SAP proposes to use for streamlined implementation and operations within Premium Engagements?
There are 2 correct answers to this question.
Response:

Question33: What is the best target deployment option of SAP S/4HANA for the "System Conversion" transition path?
Please choose the correct answer.
Response:

Question34: What is the purpose of the scrumboard?
Please choose the correct answer.
Response:

Question35: How would you describe the Explore phase in the "New Implementation of SAP S/4HANA Cloud" transition path?
Please choose the correct answer.
Response:

Question36: What term is used for a Ready-to-run SAP S/4HANA system with pre-built Solution Documentation, which supports End-to-End Processes for a specific industry so that the Project Team can focus on differentiation and innovation?
Please choose the correct answer.
Response:

Question37: Which of the following statements about Scrum is correct?
Please choose the correct answer.
Response:

Question38: Which navigation option do you use in the Roadmap Viewer to access the SAP Activate Methodology content?
Please choose the correct answer.
Response:

Question39: What tool would you use for managing project tasks and Solution Documentation when implementing SAP S/4HANA Cloud?
Please choose the correct answer.
Response:

Question40: Which artifacts are part of the Solution Adoption work stream?
There are 3 correct answers to this question.
Response:

Question41: In SAP Activate, what tool is used in the during the Realize phase to make forecasts based on actual data?
Please choose the correct answer.
Response:

Question42: Which component of SAP Activate offers customers a reference solution in the cloud for a quick start?
Please choose the correct answer.
Response:

Question43: Which tools does SAP Activate provide to support Guided Configuration?
There are 3 correct answers to this question.
Response:

Question44: What is the basis for approving work results (signing Act of Acceptance) on a Project Phase level?
Please choose the correct answer.
Response:

Question45: Which of the following Key Deliverables do you complete in the Solution Design work stream in the Explore phase?
There are 3 correct answers to this question.
Response:

Question46: What are the responsibilities of the Project Team on level 4 in the picture below?

There are 2 correct answers to this question.
Response:

Question47: Which activities are part of the Design and Configuration application of the SAP Activate methodology?
There are 2 correct answers to this question.
Response:

Question48: Which of the following is not correct about workstreams?
There are 2 correct answers to this question.
Response:

Question49: How can SRCUM teams be organized?
Please choose the correct answer.
Response:

Question50: Which Value Chains does SAP Solution Manager 7.2 deliver?
There are 3 correct answers to this question.
Response:

Question51: What are some of the key characteristics of the implementation approach in SAP Activate Methodology?
There are 3 correct answers to this question.
Response:

Question52: What do you do during an iterative approach to build a solution?
Please choose the correct answer.
Response:

Question53: When do you perform User Acceptance Testing during the Agile Build?
Please choose the correct answer.
Response:

Question54: Which of the following tools are used for rapid database migration?
There are 2 correct answers to this question.
Response:

Question55: Which deliverable is specific to on-premise and NOT for the cloud?
Please choose the correct answer.
Response:

Question56: What is a deliverable of the Application. Customer Team Enablement work stream in the Prepare phase of SAP Activate?
Please choose the correct answer.
Response:

Question57: In SAP Activate, what replaces the detailed Blueprint from ASAP?
Please choose the correct answer.
Response:

Question58: What is the term used for workshops, which are intended to set value targets, validate SAP Standard functionality against customer requirements.
And collect delta requirements in the "New Implementation of SAP S/4HANA" transition path?
Please choose the correct answer.
Response:

Question59: What are the benefits of the SAP best practices?
There are 3 correct answers to this question.
Response: